Summary - The document provides an account of the project of the Bribano-Agordo railway line from the earlystages of the concept design until the opening to commercial traffic and subsequent closure included the analysis the projects after the closure of the route. It analyzed aspects about historical and geographical context, the location, the construction phase, the commissioning and the operation of the railway line and the subsequent closure. The Bribano-Agordo railway was a 28.9 km [17.96 mi] long concession railway that connected the National FS network, via Sedico-Bribano station to the area of Agordo pyrite mines.